Pass C-TSCM42-67 Exam with Updated C-TSCM42-67 Exam Dumps PDF 2022
C-TSCM42-67 Exam Dumps - Free Demo & 365 Day Updates
SAP C-TSCM42-67 Exam Description:
The certification "SAP Certified Application Associate - Production Planning & Manufacturing with SAP ERP 6.0 EHP7" verifies the knowledge in the area of Production for the consultant profile. This certificate proves that the candidate has a basic understanding within this consultant profile and can implement this knowledge practically in projects. The SAP Certified Application Associate can contribute to the success of the planning and implementation phases of the project in a mentored role and would typically have a maximum of three years experience in the solution area. Project experience should not be prerequisite for a competent and well trained candidate to pass this exam.
NEW QUESTION 47
You use a planning time fence and fixing type 1. You receive a customer order with a material availability date within the planning time fence.
What do you have to consider in this scenario?
- A. Planned orders are created within the planning time fence and automatically firmed by requirements planning.
- B. The MRP controller cannot create planned orders within the planning time fence.
- C. Planned orders that are created by requirements planning are shifted to the end of the planning time fence.
- D. Requirements planning considers only changes that are relevant for scheduling within the planning time fence.
Answer: C
NEW QUESTION 48
What are the names of the objects for process integration of production orders? (Choose two)
- A. PI sheets
- B. Work instructions
- C. Control recipes
- D. Control instructions
Answer: B,D
NEW QUESTION 49
Which of the following items of master data are needed for repetitive manufacturing? (Choose three)
- A. Master record for serial numbers
- B. Production version
- C. Product cost collector
- D. Production supply area
- E. Repetitive manufacturing profile
Answer: B,C,E
NEW QUESTION 50
What can you use to organize material staging for production orders? (Choose three)
- A. Transfer orders
- B. Material documents
- C. Pull list
- D. Logistics Information System (LIS)
- E. KANBAN
Answer: A,C,E
NEW QUESTION 51
Which of the following statements is true for the ATP (available to promise) availability check in SAP ECC that is triggered from a customer order?
- A. An availability check by means of ATP creates fixed links between customer orders and their confirmed receipts.
- B. The ATP quantity is the quantity still available that can be used to confirm incoming customer orders.
- C. If the ATP check establishes non-availability, it checks whether it is still possible to procure or produce in time.
- D. The ATP check does not confirm against stocks and receipts, it checks consumption against planning requirements.
Answer: B
NEW QUESTION 52
In SAP ECC, you calculate the standard available capacity for a work center capacity using the following data:
- Start: 7:00:00 a.m.
- End: 3:00:00 p.m.
- Break duration: 1 hour
- Rate of utilization: 80%
- Overload: 110%
- Number of individual capacities: 1
How large is the standard available capacity?
- A. 6.16 hours
- B. 8 hours
- C. 7 hours
- D. 5.6 hours
Answer: D
NEW QUESTION 53
Which activities lead to a reduction of the capacity requirements for an operation? (Choose three)
- A. Posting the goods receipt for the production order
- B. Rescheduling the operation
- C. Reducing the order quantity
- D. Confirming the operation
- E. Setting the status technically complete (TECO)
Answer: C,D,E
NEW QUESTION 54
Which of the following statements about consumption are correct? (Choose two)
- A. Consumption can take place between order reservations and planned independent requirements, depending on the strategy.
- B. Consumption is restructured with the planning run.
- C. Consumption takes place on the material level between the planned independent requirements and the planned orders.
- D. Consumption parameters (consumption mode and consumption interval) can be set in the material master or in the MRP group.
Answer: A,D
NEW QUESTION 55
Which property applies for consumption with planning strategy 40 (planning with final assembly)?
- A. Consumption can increase the total originally planned production quantity.
- B. Consumption creates a static and binding assignment between the planned independent requirements and the customer requirements for the entire procurement process.
- C. Consumption can reduce the total originally planned production quantity.
- D. Consumption takes place with the planning material.
Answer: A
NEW QUESTION 56
What could be a consequence of confirming an operation?
- A. The capacity requirements are updated
- B. The production order is rescheduled
- C. The planned costs are updated
- D. The actual costs are settled
Answer: A
NEW QUESTION 57
Which of the following scheduling types can only be used in capacity planning?
- A. Only capacity requirements
- B. Midpoint
- C. Forward
- D. Backward
Answer: B
NEW QUESTION 58
During a project phase, your customer raises some questions concerning parameters of the procurement type in the material master in the SAP ECC system.
Which of the following procurement type properties are valid? (Choose two)
- A. Procurement types E (in-house production) and F (external procurement) always have to be further refined with special procurement types.
- B. If procurement type E (in-house production) is set, external procurement may still be possible, depending on the material type.
- C. If both procurement types are allowed with entry X (both procurement types), requirements planning assumes in-house production.
- D. Procurement types E (in-house production), F (external procurement), or X (both procurement types) can be selected for a material independent of the material type.
Answer: B,C
NEW QUESTION 59
The master data for an in-house production process is to be set up in the SAP ECC system. To do this, you should create a suitable routing that plans for five operations in an initial sequence (10, 20, 30, 40, 50). There should be an option of relocating operations 30 and 40 to a second sequence on other work centers if there are capacity bottlenecks. What sequence type would you use to create the second sequence in the system?
- A. Substitute sequence
- B. Alternative sequence
- C. Standard sequence
- D. Parallel sequence
Answer: B
NEW QUESTION 60
Which activity can trigger an automatic availability check for the components of a production order?
- A. Order rescheduling
- B. Goods receipt for a missing part
- C. Material staging
- D. Order release
Answer: D
NEW QUESTION 61
Which functions can be triggered before releasing a production order? (Choose three)
- A. Selection of a BOM
- B. Confirmation
- C. Selection of a routing
- D. Stock determination
- E. Scheduling
Answer: A,C,E
NEW QUESTION 62
Which of the following requirements for a manufacturing plant can be supported by using process manufacturing? (Choose three.)
- A. Variable calculation of material quantities (product output, material usage).
- B. Manufacturing in charge quantities.
- C. Manufacturing without orders.
- D. Master recipe-based manufacturing.
- E. Material requirements planning for production resources.
Answer: A,B,D
NEW QUESTION 63
A material was planned in the context of SAP ECC material requirements planning. The MRP controller subsequently processed the material by manually converting a specific planned order into a production order.
The MRP controller now accesses the current stock/requirements list and the MRP list for this material and compares these two lists.
What do you have to consider for the two lists at this stage? (Choose two)
- A. The stock/requirements list was updated the moment it was accessed.
- B. The MRP list displays the production order.
- C. The stock/requirements list displays the production order.
- D. The MRP list has the status "processed".
Answer: A,C
NEW QUESTION 64
In which master data object do you set the standard values for an operation?
- A. Production Resource/Tool (PRT)
- B. Material Master
- C. Routing
- D. Work Center
Answer: C
NEW QUESTION 65
......
SAP C-TSCM42-67 Exam Syllabus Topics:
| Topic | Details |
|---|---|
| Topic 1 |
|
| Topic 2 |
|
| Topic 3 |
|
| Topic 4 |
|
C-TSCM42-67 Dumps - Pass Your Certification Exam: https://examtorrent.actual4test.com/C-TSCM42-67_examcollection.html